Wyandot Solar
Type of Construction
Build 10.01 MW (AC) Photovoltaic (PV) Facility with the following site work:
- Construct road ways and storage areas for facility
- Reclaim storage areas at end of project
- Seed and landscape entire facility
- Install direct buried posts for array racking
- Install racking to house PV modules
- Install PV Modules
- Install PV Inverters
- Install A/C medium voltage collector cable
- Install all D/C cabling for facility
- Install overhead distribution line from PV to facility to utility interconnection point
Project Size
80 acres of land consumed by the facility and construction area.
Contract Value
$4.4 million
Facility Features
- 12,736 posts driven by Vaughn Industries to serve as PV array foundations
- 3,184 aluminum racks installed by Vaughn Industries on posts to house PV Modules
- 159,200 PV Modules Installed by Vaughn Industries
- >1.2 million feet of PV array feeder cable installed by Vaughn Industries
- Approximately 135,500 feet of D/C feeder cable installed by Vaughn Industries
- Approximately 20,000 feet of A/C medium voltage cable installed by Vaughn Industries
- Approximately 5 miles of overhead distribution to connect PV facility to utility
Project Duration
From late October 2009 to late May 2010: 7 months total.
Percentage of Self-Performed Work
Vaughn Industries completed approximately 90% of all work involved.
Construction Opportunities
Several RFP’s were sent to various union and non-union companies for site work, fence, landscaping activities, and various other tasks for the project. The following non-union companies were awarded various tasks for the project-Fremont Fence Company (fence work), Koehler Engineering (surveying services), Danner’s Towing & Recycling (dunnage refuse), Double K Sanitations (dunnage refuse), Kirby’s Sand and Gravel (trucking services and material supply), Machinery Movers (crane operations) and Shaferly Excavating (directional drilling services).