Findlay to Fifth 69kv Underground Line

Installing .83 miles of underground 69KV duct bank, two power vaults and two riser poles.  Pulling of 3″ diameter Prysmian 69KV underground cable, splicing and terminating that cable in the power vaults and on the riser poles.

PROJECT PHOTO GALLERY

Awarded Packages:

Duct Bank Install
Excavations
Foundations
Cable pulling
Splicing & Terminating
Installed Two Riser Poles
Transmission Line Work