- This work was completed in about 3 months with anywhere from a 4-6 man crew facing many material issues as well as steel issues that came faulty from the manufacturer. The crew did a good job and the Customer was very happy with the final product.
- This work was completed in about 3 months with anywhere from a 4-6 man crew facing many material issues as well as steel issues that came faulty from the manufacturer. The crew did a good job and the Customer was very happy with the final product.
- This work was completed in about 3 months with anywhere from a 4-6 man crew facing many material issues as well as steel issues that came faulty from the manufacturer. The crew did a good job and the Customer was very happy with the final product.
Apperson Way 69kV Station
New build 69kv Substation. Vaughn was responsible for all of the above grade work including Setting steel, Equipment, Bus work, all Control cable pulling and terminating and above grade grounding.
Biers Run Substation
Location: Chillicothe, Ohio
Type of Work: Construct a new electrical substation
Size of Project: A 7 acre substation transforming 345kv down to 138kv and 69kv
- Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring. - Duties Performed: This is an upgrade to the existing 765,000/138,000kv station. Job consists of replacing the existing 765/138 transformer bank with new transformer bank plus spare, adding new interior and exterior 765kv deadend structures, adding 5 new 765kv breakers and associated equipment.
We will also be rebuilding the 138,000kv portion of the station. This would include adding new 138kv breaker strings and replacing existing. Totally 9 new 138kv breakers and associated equipment.
Installing 2 new control buildings including all the cabling and wiring.
North Proctorville
Location: Proctorville Ohio
Type of Work: Substation Upgrade
Size of Project: 2-3 years of work for roughly 30 crew members broke down into multiple crews on the same site
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
- Duties Performed: Don Marquis is a 765,000 volt station that will have 4 new transformers that drop voltage down to 345,000 volts and transition down a hill to the 345kv substation located in the same yard. Some of the equipment is new to AEP and to Vaughn Industries.
AEP Don Marquis Substation
Location: Piketon, Ohio
Type of Work: Blanket contract with AEP to replace 345,000 and 765,000 volt transformers and installation of new equipment associated with them
AEP Malizewski 765kv
Location: Lewis Center, Ohio
Type of Work: High Voltage Substation Maintenance
Size of Project: 3 day job to replace a vertical strain bus assembly of the dual conductor 4326.9kcmil bus on the Marysville Circuit
- Duties Performed: Added 116 total Pier foundations, and 14 Slab Foundations for a total of approx 410 cyds of concrete. Installed 4 new 345Kv Circuit Breakers, 3 138Kv Circuit Breakers, 8 new 345Kv Switches, 2 138Kv Switches, and 1 345Kv Ground Switch. Also installed over 5000 ft of tubular bus and wire bus combined. Installed 23 panels in the control building and demoed and removed many more! Installed nearly 900 feet of Plastibeton (Cable Trench) and pulled many miles of control cable to new and existing equip. and terminated both ends!
Bixby Substation
Location: Groveport, Ohio
Type of Work: Expansion on 345Kv and 138Kv stations
Size of Project: 345Kv and 138Kv
- Duties Performed: Foundation installation (approx.7,000 cubic yards of concrete), Steel erection (including 12, 175’ tall structures), High tension bus work installation (including dual conductor 4326.9kcmil AAC strain bus installed at 12,000# tension),Tubular aluminum bus installation(1200’ of 5”, 9930’ of 6”),
- Duties Performed: Foundation installation (approx.7,000 cubic yards of concrete), Steel erection (including 12, 175’ tall structures), High tension bus work installation (including dual conductor 4326.9kcmil AAC strain bus installed at 12,000# tension),Tubular aluminum bus installation(1200’ of 5”, 9930’ of 6”),
- Duties Performed: Foundation installation (approx.7,000 cubic yards of concrete), Steel erection (including 12, 175’ tall structures), High tension bus work installation (including dual conductor 4326.9kcmil AAC strain bus installed at 12,000# tension),Tubular aluminum bus installation(1200’ of 5”, 9930’ of 6”),
- Duties Performed: Foundation installation (approx.7,000 cubic yards of concrete), Steel erection (including 12, 175’ tall structures), High tension bus work installation (including dual conductor 4326.9kcmil AAC strain bus installed at 12,000# tension),Tubular aluminum bus installation(1200’ of 5”, 9930’ of 6”),
- Duties Performed: Foundation installation (approx.7,000 cubic yards of concrete), Steel erection (including 12, 175’ tall structures), High tension bus work installation (including dual conductor 4326.9kcmil AAC strain bus installed at 12,000# tension),Tubular aluminum bus installation(1200’ of 5”, 9930’ of 6”),
AEP Vassell Substation
Location: Sunbury, Ohio
Type of Work: New Build Substation
Size of Project: 30 acre 765kv substation and a 30 acre 345kv/138kv substation
- Duties Performed on Job: Complete station design and build.
- Duties Performed on Job: Complete station design and build.
- Duties Performed on Job: Complete station design and build.
- Duties Performed on Job: Complete station design and build.
- Duties Performed on Job: Complete station design and build.
- Duties Performed on Job: Complete station design and build.
- Duties Performed on Job: Complete station design and build.
IS 37
Location: Morven, NC
Type of Work: Substation for 110mw Solar Project
Size of Project: 5,000,000.00